Home » Project News » Construction Update

Construction Update

  • Construction Update: Fall 2023 (9/29/2023) - Viaduct Rehabilitation, Expressway Paving Completed Punch list items to be completed and the Cayuga Street ramp reopened later this fall …
  • Construction Update: Summer 2023 (7/13/2023) - Viaduct Rehabilitation Project Substantially Completed; Expressway Paving This Summer July 13, 2023 – PennDOT’s contractor removed the temporary construction barrier and…
  • Construction Update: Spring 2023 (3/22/2023) - Final Stage of Viaduct Construction Underway The contractor in early spring began Stage 6 construction (see Stage 6 Traffic Pattern below),…
  • WAV Construction Update: Winter 2022-23 (1/3/2023) - Stage 5 Northbound Deck Construction Continues this Winter Stage 5 construction continues this winter as workers rehabilitate the outer northbound lane,…
  • WAV Construction Update: Fall 2022 (11/1/2022) - Stage 5 Construction Underway The contractor this summer concluded Stage 4 construction and began Stage 5 work this fall to rehabilitate the outer…
  • Construction Update: Summer 2022 (7/23/2022) - Inner Northbound Lane Paving Underway Shift to Next Construction Stage (5) Later This Summer Workers completed the removal of the…
  • Construction Update: Spring 2022 (4/15/2022) - Northbound Rehabilitation Underway With construction of the southbound side of the U.S. 1 (Roosevelt Expressway) viaduct over SEPTA and the…
  • Construction Update: Winter 2021-22 (1/5/2022) - Southbound Right Lane Paving Nearing Completion Paving operations on the southbound right lane of the U.S. 1/Roosevelt Expressway viaduct over…
  • Construction Update: Fall 2021 (10/22/2021) - Paving this Fall on Viaduct’s Southbound Right Lane Rehabilitation continues on the U.S. 1/Roosevelt Expressway viaduct over SEPTA and the…
  • Construction Update: Summer 2021 (6/29/2021) - Stage Three Construction Begins This Summer Rehabilitation of the southbound left lane of the U.S. 1/Roosevelt Expressway viaduct over SEPTA…