The Pennsylvania Department of Transportation (PennDOT) announced today that overhead sign installation will continue on U.S. 1 (Roosevelt Expressway) under…
The Pennsylvania Department of Transportation (PennDOT) announced today that construction activities will continue under the substantially completed project to replace…
The Pennsylvania Department of Transportation (PennDOT) announced today that the bridge that carries the southbound U.S. 13/Hunting Park Avenue ramp over U.S.…
The Pennsylvania Department of Transportation (PennDOT) announced today that the ramp from Cayuga Street to southbound U.S. 1 (Roosevelt Expressway)…
The Pennsylvania Department of Transportation (PennDOT) announced today that the ramp from southbound U.S. 1 (Roosevelt Expressway) to westbound Interstate…
Viaduct Rehabilitation, Expressway Paving Completed Punch list items to be completed and the Cayuga Street ramp reopened later this fall …
Viaduct Rehabilitation Project Substantially Completed; Expressway Paving This Summer July 13, 2023 – PennDOT’s contractor removed the temporary construction barrier and…
Harrisburg, PA – The Pennsylvania Department of Transportation (PennDOT) announced today that the Pennsylvania State Senate has confirmed Michael B. Carroll as the…
Final Stage of Viaduct Construction Underway The contractor in early spring began Stage 6 construction (see Stage 6 Traffic Pattern below),…
Stage 5 Northbound Deck Construction Continues this Winter Stage 5 construction continues this winter as workers rehabilitate the outer northbound lane,…